Madera Power - Firebaugh, California
Project Date: 2007 - 2008
Details: Madera Power experienced a fire involving their Turbine/Generator.
Yanke Energy assisted in locating a surplus Turbine/Generator set in Michigan. We had personnel on-site through out the removal, packaging & shipment.
The engineering department assisted Madera Power with mass flow calculations for determining the best heaters, pumps to utilize. Our electrical department generated updated One-Line & Three Line diagrams in order for the different generation equipment to be tied into the existing substation.
Our field crew, millwrights, fitters, welders and electricians worked alongside plant operations staff to put the plant back on-line. Field engineers were on site throughout the rebuild and start-up process.